Project number 6409/2
Project name

Eden Beach Estate Beach Access Node

Project status Current
Proponent(s) Satterley Property Group Pty Ltd
Project location

Lot 3052 on Deposited Plan 47953, Jindalee
Lot 15450 on Deposited Plan 40341, Jindalee

Project bioregion(s) Swan Coastal Plain
Assessment criteria (h) the clearing of the vegetation is likely to have an impact on the environmental values of any adjacent or nearby conservation area.
Residual impact

Loss of up to 2.1 hectares of native vegetation from Bush Forever site 397 known as 'Coastal strip from Wilbinga to Mindarie'

Offset conditions

Condition 7:
Prior to undertaking any clearing authorised under this Permit and no later than 11 April 2016, the Permit Holder shall provide documentary evidence to the CEO that funding of $45,259 has been transferred to the Department of Environment Regulation for the purpose of establishing or maintaining vegetation.

Statutory process EP Act Clearing (Part V)
Approved project area (ha) 2.1

Decision(s):

DECISION 1
Date: 2015-05-21 Ministerial statement: None
OFFSET 1
Condition status: Complete
Type(s): Land acquisition
Rationale:

The offset involves the acquisition of 3.15 hectares of native vegetation with similar values to that being cleared. The offset is considered to be relevant and proportionate to the significance of the environmental values being impacted, mitigating the residual impacts of the project.

Security arrangements:

The land to be acquired will be vested with and managed by the Department of Parks and Wildlife for conservation.

Governance arrangements:

Offset location:

Once acquired, location details will be published on the offsets register.

Approved offset area (ha): 3.15
Bioregion(s): Swan Coastal Plain
Delivery agent:

CONDITION MILESTONE 1
Milestone:

Condition Milestone 1 - relates to permit condition 7
 
The Permit Holder shall provide documentary evidence to the CEO that funding of $45,259 has been transferred to the Department of Environment Regulation for the purpose of establishing or maintaining vegetation.

Timeframe:

Prior to undertaking any clearing authorised under the permit and no later than 11 April 2016.

Timeframe (date): 2016-04-11
Complete: Yes
IMPLEMENTATION MILESTONE 1
Milestone:

Implementation Milestone 1
 
Department of Environment Regulation to purchase 3.15 hectares of native vegetation with similar values to the vegetation to be cleared.

Timeframe:

Complete: No