Project number 6628/1
Project name

Alkimos Beach Southern Access Track

Project status Current
Proponent(s) Western Australian Land Authority T/A Landcorp
Project location

Lot 9025 on Deposited Plan 405189, Alkimos

Project bioregion(s) Swan Coastal Plain
Assessment criteria (h) the clearing of the vegetation is likely to have an impact on the environmental values of any adjacent or nearby conservation area.
Residual impact

Loss of up to 1.98 hectares of native vegetation in very good (Keighery 1994) condition that includes 1.2 hectares of Bush Forever site 397 'Coastal strip from Wilbinga to Mindarie'.

Offset conditions

Condition 7:
Prior to undertaking any clearing authorised under this Permit and no later than 17 October 2016, the Permit Holder shall provide documentary evidence to the CEO that funding of $25,862 has been transferred to the Department of Environment Regulation for the purpose of establishing or maintaining vegetation.

Statutory process EP Act Clearing (Part V)
Approved project area (ha) 1.98

Decision(s):

DECISION 1
Date: 2015-09-17 Ministerial statement: None
OFFSET 1
Condition status: Complete
Type(s): Land acquisition
Rationale:

The offset involves the acquisition of 1.8 hectares of native vegetation with similar values to that being cleared. The offset is considered to be relevant and proportionate to the significance of the environmental values being impacted, mitigating the residual impacts of the project.

Security arrangements:

Details to be published upon completion of the land acquisition process.

Governance arrangements:

Offset location:

Once acquired, location details will be published on the offsets register.

Approved offset area (ha): 1.8
Bioregion(s): Swan Coastal Plain
Delivery agent:

CONDITION MILESTONE 1
Milestone:

Condition Milestone 1
 
The Permit Holder shall provide documentary evidence to the CEO that funding of $25,862 has been transferred to the Department of Environment Regulation for the purpose of establishing or maintaining vegetation.

Timeframe:

Prior to undertaking any clearing authorised under the permit and no later than 17 October 2016.

Timeframe (date): 2016-10-17
Complete: Yes
IMPLEMENTATION MILESTONE 1
Milestone:

Implementation Milestone 1

Department of Environment Regulation to purchase 1.8 hectares of native vegetation with similar values to the vegetation to be cleared.

Timeframe:

Complete: No