Project number OEPA:155
Project name

Eglinton Beach Proposal

Project status Current
Proponent(s) Eglinton Estates Pty Ltd (ACN: 009 460 397)
Project location

Eglinton

Project bioregion(s) Swan Coastal Plain
Assessment criteria Coastal Processes, Flora and Vegetation
Residual impact

Following implementation of avoidance and mitigation measures, the proposal will have the following significant residual impacts:
- Loss of public foreshore area
- Impact to high conservation value coastal dunes (Quindalup dune system)

Offset conditions

5 Terrestrial Flora and Vegetation (Conservation Areas)

5-1 The proponent shall conserve the flora, vegetation and dune systems within the Conservation areas shown in Figure 1 of Schedule 1.

5-2 By 01 September 2015, unless agreed by the CEO, the proponent shall prepare in consultation with the Department of Parks and Wildlife and to the satisfaction of the CEO, a Conservation Area Management Plan for the Conservation areas (A, B, C & D) shown in Figure 1 of Schedule 1, and spatially defined in Schedule 3.

5-3 The proponent shall cede the Conservation areas identified in Figure 1 of Schedule 1 to a management authority approved by the CEO within 10 years of approval of the plan required in Condition 5-2.

5-4 The Conservation Area Management Plan required by Condition 5-2 shall include but is not limited to the following details:
(1) fencing, access and signage;
(2) rehabilitation and revegetation;
(3) measures to control vehicle and pedestrian access;
(4) limited passive recreation;
(5) weed control;
(6) bushfire management;
(7) feral animal control;
(8) completion criteria for handover to a management authority; and
(9) management measures to ensure impacts from the proposal are contained within the development envelope shown in Figure 1.

5-5 The proponent shall implement the approved Conservation Area Management Plan for 10 years from the date of approval of the plan or until such time as the land is ceded to a management authority approved by the CEO, whichever is sooner.

Statutory process EP Act Environmental Impact Assessment (Part IV)
Approved project area (ha) 246.8

Decision(s):

DECISION 1
Date: 2015-01-05 Ministerial statement: 992
OFFSET 1
Condition status: Current
Type(s): Land acquisition, Onground management
Rationale:

The land acquisition and on-ground management offset is an appropriate offset as it will ensure that there is no loss of public land, as well as ensure the preservation and ongoing maintenance of high quality dune systems in situ.

Security arrangements:

Land to be ceded to the Crown.

Governance arrangements:

A Conservation Management Plan will be prepared for the area in consultation with the Department of Parks and Wildlife.

Offset location:

Eglinton

Approved offset area (ha): 47.0
Bioregion(s): Swan Coastal Plain
Delivery agent:

Eglinton Estates Pty Ltd.

CONDITION MILESTONE 1
Milestone:

01 The proponent shall prepare, in consultation with the Department of Parks and Wildlife, a Conservation Area Management Plan for the Conservation areas.

Timeframe:

01 September 2015

Timeframe (date): 2015-09-01
Complete: Yes
CONDITION MILESTONE 2
Milestone:

02 The proponent shall cede the Conservation areas identified in Figure 1 of Schedule 1 to a management authority approved by the CEO within 10 years of approval of the plan required in Condition 5-2.

Timeframe:

Within 10 years of approval of the plan required in Condition 5-2.

Timeframe (date): 2026-06-13
Complete: Unknown
IMPLEMENTATION MILESTONE 1
Milestone:

Implement approved Conservation Area Management Plan

Timeframe:

For 10 years or until conservation areas are ceded to a management authority approved by the CEO of the OEPA.

Complete: Unknown