Project number | OEPA:21 |
---|---|
Project name | Cloudbreak Life of Mine, Pilbara |
Project status | Current |
Proponent(s) | Fortescue Metals Group Ltd |
Project location | Approximately 100 km NNW of Newman |
Project bioregion(s) | Pilbara |
Assessment criteria | Flora and Vegetation, Terrestrial Fauna |
Residual impact | Following the implementation of all mitigation measures, the Expansion Proposal would have the following significant residual impacts: Direct and indirect impacts to: Direct and indirect impacts to habitats of conservation significant species: While the project footprint is up to 13,633 ha, 5,500 ha applies to the Existing Mine and 8,133 ha applies to the Expansion (i.e. this project). |
Offset conditions | 15-1 In view of the residual impacts and risks to high value environmental assets and Matters of National Environmental Significance adjacent to the nationally important Fortescue Marsh wetland and within and adjacent to the proposed 15-2 Notwithstanding the requirements of Table 1 in Schedule 1 and condition 6, the proponent’s contributions to the strategic regional conservation initiative for the Pilbara determined pursuant to condition 15-1 will be made on the following basis: 15-3 By 30 September 2012, the proponent shall develop, for the approval of the CEO, an Impact Reconciliation Procedure to determine, on a biennial basis, the extent of impacts that have occurred that will be the basis for the contributions required by condition 15-2. 15-4 The proponent shall implement the Impact Reconciliation Procedure required by condition 15-3 and submit the results to the CEO for approval at least two months prior to providing the contribution as required by condition 15-2. 15-5 The real value of annual contributions described in 15-2 will be maintained through indexation to the Perth consumer price index (CPI), with the first adjustment to be applied to the initial contribution for direct impacts that is to 15-6 The proponent shall make the results of the Impact Reconciliation Procedure required by condition 15-4 publicly available in a manner approved by the CEO. Note: Where the proponent is to contribute for indirect impacts, this refers to indirect impacts outside of the Mine Envelope as shown in Figure 1 and delineated by the co-ordinates in Schedule 3. Schedule 1, condition 6, Figure 1 and Schedule 3 - see Ministerial Statement. |
Statutory process | EP Act Environmental Impact Assessment (Part IV) |
Approved project area (ha) | 13633.0 |
DECISION 1 | ||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Date: 2012-06-01 | Ministerial statement: 899 | |||||||||||||||||||||||||||||||||
|