Project number 3544/1
Project name

GMA Garnet has applied to clear up to 34.938 hectares within an area of 34.938 hectares for the purposes of mineral sand mining. The application area is located approximately 12 kilometres north of Port Gregory (GIS Database). Clearing will be by mechanical means.

Project status Current
Proponent(s) GMA Garnet Pty Ltd
Project location

M 7000927
M 7000856

Project bioregion(s) Geraldton Sandplains
Assessment criteria (e) it is significant as a remnant of native vegetation in an area that has been extensively cleared.
Residual impact

Loss of 33.227 ha of remnant vegetation in an extensively cleared landscape.
Loss of 33.227 ha of Beard vegetation association 371 which has only 10.1% of its pre-Eurpean extent remaing
Loss of 33.227 ha of vegetation that provides an ecological linkage between dune systems in the east and coastal plains in the west.

Offset conditions

Offsets
6. If part or all of the clearing to be done is or may be at variance with one or more of the clearing principles, then the Permit Holder must implement an offset in accordance with Conditions 6(a) and (b) of this Permit with respect to that clearing.

(a) Determination of offsets:
(i) in determining the offset to be implemented with respect to a particular area of native vegetation proposed to be cleared under this Permit, the Permit Holder must have regard to the offset principles contained in Condition 6(b) of this Permit;
(ii) once the Permit Holder has developed an offset proposal, the Permit Holder must provide that offset proposal to the Director, Environment Division, Department of Mines and Petroleum for the Director, Environment Division, Department of Mines and Petroleum’s approval prior to undertaking any clearing to which the offset relates, and prior to implementing the offset;
(iii) clearing may not commence until and unless the Director, Environment Division, Department of Mines and Petroleum has approved the offset proposal to which the clearing relates;
(iv) the Permit Holder shall implement the offset proposal approved under Condition 6(a)(iii); and
(v) each offset proposal shall include a direct offset, timing for implementation of the offset proposal and may additionally include contributing offsets.

(b) For the purpose of this condition, the offset principles are as follows:
(i) direct offsets should directly counterbalance the loss of the native vegetation;
(ii) contributing offsets should complement and enhance the direct offset;
(iii) offsets are implemented only once all avenues to avoid, minimise, rectify or reduce environmental impacts have been exhausted;
(iv) the environmental values, habitat, species, ecological community, physical area, ecosystem, landscape, and hydrology of the offset should be the same as, or better than, that of the area of native vegetation being offset;
(v) a ratio greater than 1:1 should be applied to the size of the area of native vegetation that is offset to compensate for the risk that the offset may fail;
(vi) offsets must entail a robust and consistent assessment process;
(vii) in determining an appropriate offset, consideration should be given to ecosystem function, rarity and type of ecological community, vegetation condition, habitat quality and area of native vegetation cleared;
(viii) the offset should either result in no net loss of native vegetation, or lead to a net gain in native vegetation and improve the condition of the natural environment;
(ix) offsets must satisfy all statutory requirements;
(x) offsets must be clearly defined, documented and audited;
(xi) offsets must ensure a long-term (10-30 year) benefit; and
(xii) an environmental specialist must be involved in the design, assessment and monitoring of offsets.

Statutory process EP Act Clearing (Part V)
Approved project area (ha) 33.227

Decision(s):

DECISION 1
Date: 2010-04-01 Ministerial statement: None
OFFSET 1
Condition status: Current
Type(s): Land acquisition, Other, Restoration
Rationale:

In 2007 GMA Garnet Pty Ltd purchased 164.3 ha of land which has been added to Utcha Well Nature Reserve (Lot 100 on Plan 40730). The acquisition of this land involved the excision of 37.2 ha of poorer quality vegetation from Utcha Well Nature Reserve east of George Grey Drive. The excised land is now part of freehold land held by GMA Garnet Pty Ltd. The vegetation within the permit area is in good to degraded condition with a high level of weed infestation. GMA Garnet Pty Ltd will develop a rehabilitation plan that will restore the cleared area to a better than current condition. This will include fencing the area off from livestock, actively managing weeds and continual monitoring of vegetation regrowth.

Security arrangements:

Lot 100 on Plan 40730 is held by the Department of Environment and Conservation.
Mining Lease 70/927 and the underlying Lot 1 on Plan 59630 are held by GMA Garnet Pty Ltd.

Governance arrangements:

Utcha Well Nature Reserve is managed by the Department of Parks and Wildlife.
The restoration on Mining Lease 70/927 will be managed by GMA Garnet Pty Ltd.

Offset location:

Lot 100 on Plan 40730 and Mining Lease 70/927.

Approved offset area (ha): 164.3
Bioregion(s): Geraldton Sandplains
Delivery agent:

GMA Garnet Pty Ltd

CONDITION MILESTONE 1
Milestone:

Offset proposal is developed and submitted for approval.

Timeframe:

Prior to clearing commencing.

Complete: Yes
IMPLEMENTATION MILESTONE 1
Milestone:

Cleared vegetation is restored to better than current conditon.

Timeframe:

Progressively as area is being mined.

Timeframe (date): 2025-04-30
Complete: No
IMPLEMENTATION MILESTONE 2
Milestone:

Lot 100 on Plan 40730 is purchased and added to Utcha Well Nature Reserve.

Timeframe:

Prior to clearing.

Complete: Yes
IMPLEMENTATION MILESTONE 3
Milestone:

Rehabilitation plan is prepared.

Timeframe:

Prior to clearing

Complete: Yes
IMPLEMENTATION MILESTONE 4
Milestone:

Restored area is actively managed for weeds

Timeframe:

Once rehabilitation commences

Timeframe (date): 2025-04-30
Complete: No
IMPLEMENTATION MILESTONE 5
Milestone:

Restored area is continually monitored to ensure targets are being achieved.

Timeframe:

Ongoing.

Timeframe (date): 2025-04-30
Complete: No
IMPLEMENTATION MILESTONE 6
Milestone:

Restored area is fenced off from livestock

Timeframe:

Once rehabilitation is complete

Timeframe (date): 2025-04-30
Complete: No