Project number OEPA:19
Project name

Weld Range Iron Ore Project

Project status Current
Proponent(s) Sinosteel Midwest Corporation Limited
Project location

85km south west of Meekatharra and 60km north west of Cue in the Midwest region of Western Australia.

Approved project area (ha) 3589.0

Decision(s):

DECISION 1 Date of decision: 29 Aug 2012
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Onground management 18000.0 Current
1
Milestone:

10-2 The proponent shall prepare a plan for the program in condition 10-1 which will include:
1. the boundary of the program and the management actions to be undertaken;
2. monitoring arrangements, performance indicators and success criteria; and
3. arrangements for the continuation of the program post mine closure where any funding has not been spent.

This plan shall be determined in consultation with the Department administering the Wildlife Conservation Act 1950 or its equivalent, and approved by the CEO, prior to ground-disturbing activities.

Timeframe:

Prior to ground disturbance

Complete: No