Project number 5479/1
Project name

Clearing of 0.096 hectares of native vegetation for the purpose of road realignment in the Shire of Plantagenet.

Project status Current
Proponent(s) Shire of Plantagenet
Project location

LOT 377 ON PLAN 71527 MOUNT BARKER 6324
LOT 376 ON PLAN 71527 MOUNT BARKER 6324
ROAD RESERVE MOUNT BARKER 6324

Approved project area (ha) 0.096

Decision(s):

DECISION 1 Date of decision: 07 Mar 2013
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Rehabilitation 0.08 Current
1
Milestone:

Condition Milestone 1 - relates to Permit condition 9(a)

The Permit Holder shall retain the vegetative material and topsoil removed by clearing authorised under this Permit and stockpile the vegetative material and topsoil in an area that has already been cleared.

Timeframe:

Post clearing authorised under this Permit.

Complete: No
2
Milestone:

Condition Milestone 2 - relates to Permit condition 9(b)

The Permit Holder shall revegetate and rehabilitate the area cross-hatched red on attached Plan 5479/1 by:
(i) ripping the ground on the contour to remove soil compaction; and
(ii) laying the vegetative material and topsoil retained under condition 9(a) on the area cross-hatched red on attached Plan 5479/1.

Timeframe:

Within 2 months following completion of the clearing authorised under this permit.