Project number OEPA:94
Project name

Mangles Bay Marina Based Tourist Precinct

Project status Current
Proponent(s) Cranford Pty Ltd (Australian Company Number 009 373 068) and Western Australian Land Authority (Australian Business Number 34 868 192 835)
Project location

Mangles Bay at the southern end of Cockburn Sound

Approved project area (ha) 45.36

Decision(s):

DECISION 1 Date of decision: 19 Jun 2014
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Restoration 2.83 Current
1
Milestone:

11-01 The proponent shall develop a Threatened Ecological Community Restoration Plan in consultation with the Department of Parks and Wildlife and submit the Plan to the CEO of OEPA for approval.

Timeframe:

Twelve months prior to construction.

Complete: No
OFFSET 2 Restoration 10.48 Current
1
Milestone:

11-04 Seagrass Restoration Plan to be submitted to the CEO of OEPA.

Timeframe:

Prior to the commencement of construction.

Complete: No
OFFSET 3 Offset funds None Current
1
Milestone:

11-12 Payment of $250,000 to the Cockburn Sound Management Council.

Timeframe:

Within 12 months of commencement of construction

Complete: No
OFFSET 4 Rehabilitation 20.0 Current
1
Milestone:

11-16 The proponent shall prepare and submit a Rehabilitation Plan to the satisfaction of the Department of Parks and Wildlife and approval of the OEPA CEO.

Timeframe:

Within 12 months of the commencement of construction.

Complete: No
OFFSET 5 Land acquisition 56.0 Current
1
Milestone:

11-20 The proponent shall prepare and submit a Land Acquisition and Management Plan to the satisfaction of the CEO of the OEPA.

Timeframe:

Prior to the commencement of construction

Complete: No