Project number 980/1
Project name

Clearing of 1.4 hectares of native vegetation for the purpose of road construction or maintenance in the City of Wanneroo.

Project status Complete
Proponent(s) City of Wanneroo
Project location

LOT 970 ON PLAN 247637 GNANGARA 6065
LOT 970 ON PLAN 247637 GNANGARA 6065
LOT 51 ON DIAGRAM 65224 GNANGARA 6065
LOT 51 ON DIAGRAM 65224 GNANGARA 6065
LOT 50 ON DIAGRAM 65223 GNANGARA 6065
LOT 50 ON DIAGRAM 65223 GNANGARA 6065

Approved project area (ha) 1.4

Decision(s):

DECISION 1 Date of decision: 24 Aug 2006
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Rehabilitation 2.27 Complete
1
Milestone:

Condition Milestone 1 - relates to Permit condition 3

The Permit Holder shall retain the vegetative material and topsoil removed by clearing and shall lay the vegetative material and topsoil within the area cross hatched red on Plan 980/1 Map 1 and 980/1 Map 2 (portion of Lot 5199 on Plan 161576).

Timeframe:

Prior to the expiry of the permit.

Complete: Yes
2
Milestone:

Condition Milestone 2 - relates to Permit condition 5

The Permit Holder must revegetate the area cross hatched red on Plan 980/1 Map 1 and 980/1 Map 2 by:
(a) Deliberately planting and/or seeding native vegetation that will result in a similar species composition, structure and density of native vegetation to pre-clearing vegetation types in that area.
(b) Ensuring only local provenance seeds and propagating material from within 10 km of the proposed clearing are used to revegetate the area cross hatched in red in accordance with condition 5.

Timeframe:

Revegetation must commence by September 2007.

Complete: No
3
Milestone:

Condition Milestone 3 - relates to Permit condition 6

The Permit Holder shall construct a fence enclosing the area cross hatched red on Plan 980/1 Map 1. The fence shall be constructed and maintained so as to be adequate to exclude public vehicle access.

Timeframe:

Construction of the fence shall be completed by December 2007.

Complete: No
4
Milestone:

Condition Milestone 4 - relates to Permit condition 7

The Permit Holder must:
(a) determine the species composition, structure and density of the area revegetated in accordance with condition 5; and
(b) where, in the opinion of an environmental specialist, the composition structure and density determined under condition 7(a) will not result in a similar species composition, structure and density to pre-clearing vegetation types in that area the Permit Holder must undertake additional planting or seeding of native vegetation in accordance with the requirements of condition 5(a) and (b).

Timeframe:

Within one year of undertaking revegetation in accordance with condition 5.

Complete: No
5
Milestone:

Condition Milestone 5 - relates to Permit condition 8

The Permit Holder must remove or kill any weeds growing within areas revegetated and rehabilitated under this Permit.

Timeframe:

At least once within one year of the commencement of the Permit.

Complete: Yes