Project number OEPA:193
Project name

Orebody 31 Iron Ore Mine

Project status Current
Proponent(s) BHP Billiton Iron Ore Pty Ltd
Project location

Approximately 40 kilometres (km) east of Newman

Approved project area (ha) 4075.0

Decision(s):

DECISION 1 Date of decision: 12 Nov 2015
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Offset funds None Current
1
Milestone:

01. Prepare an Impact Reconciliation Procedure and submit it for approval of the CEO.

Timeframe:

Within 12 months of the statement.

Timeframe (date): 2016-11-12
Complete: No