Project number 4781/3
Project name

Clearing of 2.82 hectares of native vegetation for the purpose of road widening and realignment in the Shire of Bruce Rock

Project status Current
Proponent(s) Shire of Bruce Rock
Project location

Old Beverley Road Reserve, ARDATH 6419 (PIN 11657468 and 11657469)
Collier Road Reserve, BRUCE ROCK 6418 (PIN 11493051)
Kellerberrin- Shackleton Road Reserve, SHACKLETON 6386 (PIN 11648559, 11650029, 11650028, 11650030, 11650031 and 11650032)
Babakin- Corrigin Road Reserve, BABAKIN 6428 (PIN 976571, 11658101, 11716452 and 11398157)

Approved project area (ha) 2.82

Decision(s):

DECISION 1 Date of decision: 26 Feb 2015
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Rehabilitation 4.8 Current
1
Milestone:

Condition Milestone 1 - relates to Permit condition 8(a)
 
The Permit Holder must commence the revegetation project.

Timeframe:

By July 2013 or a date otherwise approved by the CEO.

Complete: Yes
2
Milestone:

Condition Milestone 2 - relates to Permit condition 8(b)
 
The Permit Holder must adhere to a starting density of 2,100 stems per hectare with an overall success rate of 75% of the 2,100 stems per hectare. 

Timeframe:

5 years after establishment.

Complete: No
3
Milestone:

Condition Milestone 3 - relates to Permit condition 8(c)
 
The Permit Holder must adhere to a composition of at least 18 local provenance species consistent with the mapped vegetation type. 

Timeframe:

5 years after establishment.

Complete: No
4
Milestone:

Condition Milestone 4 - relates to Permit condition 8(d)
 
The Permit Holder must adhere to a target structure of 25% overstorey, 50% midstorey and 25% understorey. 

Timeframe:

5 years after establishment.

Complete: No
5
Milestone:

Condition Milestone 5 - relates to Permit condition 8(e)
 
Selective weed control via hand spraying must be undertaken.

Timeframe:

As required.

Complete: No
6
Milestone:

Condition Milestone 6 - relates to Permit condition 8(f)
 
Rabbit warrens must be ripped and a baiting programme initiated if the problem persists. 

Timeframe:

Ripping - prior to revegetation works.
Baiting programme - for the term of the permit.

Complete: No
7
Milestone:

Condition Milestone 7 - relates to Permit condition 8(g)
 
Weeds and revegetation establishment to be monitored annually. 

Timeframe:

For a five year period.

Complete: No
8
Milestone:

Condition Milestone 8 - relates to Permit condition 8(h)
 
Infill planting and weed control must be undertaken. 

Timeframe:

Within 12 months of success rate in condition 8(b), 8(c) and 8(d) not being met.

Complete: No
9
Milestone:

Condition Milestone 9 - relates to Permit condition 8(i)
 
Photo points must be established at 3 sites within the project area.

Timeframe:

Photographs must be taken before planting, the summer after planting and annually, for a five year period after initial plantings, during summer.

Complete: No