Decision(s):

DECISION 1 Date of decision: 05 Dec 2013
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Offset funds, Research None Current
1
Milestone:

10-2 The proponent shall provide funding to a party approved by the CEO for development and implementation of a Wetland Research and Management Plan in accordance with the following schedule:
(1) $138,600 prior to expansion of mining outside Area A within Mining Lease 70/1161; and
(2) $138,600 within two months of disturbing more than 20 hectares outside Area A within Mining Lease 70/1161, or three years after commencement of mining outside Area A within Mining Lease 70/1161, whichever is the sooner.

Timeframe:

(1) prior to expansion of mining outside Area A within Mining Lease 70/1161; and
(2) within two months of disturbing more than 20 hectares outside Area A within Mining Lease 70/1161, or three years after commencement of mining outside Area A within Mining Lease 70/1161, whichever is the sooner.

Complete: No