Project number OEPA:36
Project name

Western Turner Syncline Iron Ore Project - Revised Proposal

Project status Current
Proponent(s) Hamersley Iron Pty Limited Australian Company Number 004 558 276
Project location

Approximately 30 km west of Tom Price, Western Australia.

Approved project area (ha) 15836.0

Decision(s):

DECISION 1 Date of decision: 22 Aug 2013
Offset Offset Type Offset Area Offset Status Condition Milestones
DECISION 2 Date of decision: 23 Jun 2016
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Offset funds None Current
1
Milestone:

Update the previously approved Impact Reconciliation Procedure (RTIO-HSE-0165630, dated 18 September 2013) and submit for approval of the CEO

Timeframe:

Within 12 months of the statement

Timeframe (date): 2017-06-23
Complete: Unknown