Project number OEPA:185
Project name

Roe Highway Extension

Project status Current
Proponent(s) Main Roads Western Australia (ABN 50 860 676 021)
Project location

From the current terminus of Roe Highway at Kwinana Freeway in Jandakot, to Stock Road in Coolbellup

Approved project area (ha) 98.75

Decision(s):

DECISION 1 Date of decision: 02 Jul 2015
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Land acquisition, Onground management 624.0 Current
1
Milestone:

01. Main Roads to submit the Land Acquisition and Management Plan to the CEO for approval.

Timeframe:

Prior to commencement of construction, as as otherwise agreed by the CEO.

Complete: Yes
2
Milestone:

02. Main Roads shall acquire or fully fund the acquisition of the two offset sites.

Timeframe:

Prior to commencement of construction, as as otherwise agreed by the CEO.

Complete: Yes
3
Milestone:

03. Main Roads shall implement the approved Land Acquisition and Management Plan.

Timeframe:

Prior to commencement of construction, as as otherwise agreed by the CEO, until the CEO advises implementation may cease.

Complete: No
OFFSET 2 Onground management, Restoration 13.4 Current
1
Milestone:

01. Submit the Wetland Restoration Plan to the CEO for approval.

Timeframe:

Prior to commencement of construction, or as otherwise agreed by the CEO

Complete: Yes
2
Milestone:

02. The proponent shall implement the Wetland Restoration Plan.

Timeframe:

Prior to commencement of construction, or as otherwise agreed by the CEO, until the CEO advises implementation may cease.

Complete: No
OFFSET 3 Land acquisition, Onground management 14.5 Current
1
Milestone:

01. Submit the Arum Lily Control Plan for the approval of the CEO.

Timeframe:

Prior to commencement of construction, or as otherwise agreed by the CEO.

Complete: Yes
2
Milestone:

02. The proponent shall commence implementation of the Arum Lily Control Program.

Timeframe:

Within twelve (12) months of completion of the proposal, until the CEO advises implementation may cease.

Complete: No
OFFSET 4 Onground management None Current
1
Milestone:

01. Submit the Typha orientalis Control Program for the approval of the CEO.

Timeframe:

Prior to commencement of construction, or as otherwise agreed by the CEO.

Complete: Yes
2
Milestone:

02. The proponent shall implement the Typha orientalis Control Program.

Timeframe:

Prior to commencement of construction, or as otherwise agreed by the CEO, until the CEO advises implementation may cease.

Complete: No