Project number OEPA:235
Project name

Mt Gibson Range Mine Operations Iron Hill Deposits

Project status Current
Proponent(s) Mount Gibson Mining Limited
Project location

Mt Gibson Range, approximately 270 kilometres east-south-east of Geraldton.

Approved project area (ha) 112.0

Decision(s):

DECISION 1 Date of decision: 08 Dec 2016
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Onground management, Other None Current
1
Milestone:

Prepare and submit a Darwinia masonii Offset Plan to the CEO, in consultation with Parks and Wildlife

Timeframe:

Within six months of issue of this Statement, or as otherwise agreed in writing by the CEO

Timeframe (date): 2017-06-08
Complete: No
OFFSET 2 Onground management, Other, Research None Current
1
Milestone:

Prepare and submit a Lepidosperma gibsonii Offset Plan to the CEO, in consultation with Parks and Wildlife.

Timeframe:

Within six months of issue of this Statement, or as otherwise agreed in writing by the CEO

Timeframe (date): 2017-06-08
Complete: No