Project number OEPA:27
Project name

Wheatstone Development - Gas Processing, Export Facilities and Infrastructure

Project status Current
Proponent(s) Chevron Australia Pty Ltd
Project location

12 kilometres south of the town of Onslow

**NB Spatial data for this proposal is approximate.

Approved project area (ha) 3300.0

Decision(s):

DECISION 1 Date of decision: 30 Aug 2011
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Offset funds, Research None Complete
1
Milestone:

22-02 1st Contribution of $1.6m to WAMSI

Timeframe:

30 January 2012.

The CEO has approved an extension of this due date to 31 May 2012

Timeframe (date): 2012-05-31
Complete: Yes
2
Milestone:

22-02 2nd Contribution of $1.6m to WAMSI

Timeframe:

30 January 2013

Timeframe (date): 2013-01-30
Complete: Yes
OFFSET 2 Offset funds, Research None Complete
1
Milestone:

22-03 1st contribution of $300,000

Timeframe:

30 January 2012

The CEO has approved an extension of this due date to 31 May 2012

Timeframe (date): 2012-05-31
Complete: Yes
2
Milestone:

22-03 2nd contribution of $300,000

Timeframe:

30 January 2013

Timeframe (date): 2013-01-30
Complete: Yes
3
Milestone:

22-03 3rd contribution of $300,000

Timeframe:

30 January 2014

Timeframe (date): 2014-01-30
Complete: Yes
4
Milestone:

22-03 4th contribution of $300,000

Timeframe:

30 January 2015

Timeframe (date): 2015-01-30
Complete: Yes
OFFSET 3 Offset funds, Research None Complete
1
Milestone:

22-04 1st contribution of $875,000

Timeframe:

30 January 2012

The CEO has approved an extension of this due date to 31 May 2012

Timeframe (date): 2012-05-31
Complete: Yes
2
Milestone:

22-04 2nd contribution of $875,000

Timeframe:

30 January 2013

Timeframe (date): 2013-01-30
Complete: Yes
3
Milestone:

22-04 3rd contribution of $875,000

Timeframe:

30 January 2014

Timeframe (date): 2014-01-30
Complete: Yes
4
Milestone:

22-04 4th contribution of $875,000

Timeframe:

30 January 2015

Timeframe (date): 2015-01-30
Complete: Yes
OFFSET 4 Offset funds, Onground management None Current
1
Milestone:

22-06 1st payment of $770,000

Timeframe:

30 January 2012

The CEO has approved an extension of this due date to 31 May 2012

Timeframe (date): 2012-05-31
Complete: Yes
2
Milestone:

22-06 2nd payment of $770,000 (indexed to CPI)

Timeframe:

30 January 2013

Timeframe (date): 2013-01-30
Complete: Yes
3
Milestone:

22-06 3rd payment of $770,000 (indexed to CPI)

Timeframe:

30 January 2014

Timeframe (date): 2014-01-30
Complete: Yes
4
Milestone:

22-06 4th payment of $770,000 (indexed to CPI)

Timeframe:

30 January 2015

Timeframe (date): 2015-01-30
Complete: Yes
5
Milestone:

22-06 5th payment of $770,000 (indexed to CPI)

Timeframe:

30 January 2016

Timeframe (date): 2016-01-25
Complete: Yes
OFFSET 5 Offset funds, Onground management None Current
1
Milestone:

22-07 1st contribution of $220,000

Timeframe:

30 January 2012

The CEO has approved an extension of this due date to 31 May 2012

Timeframe (date): 2012-05-31
Complete: Yes
2
Milestone:

22-07 2nd contribution of $220,000 (indexed to CPI)

Timeframe:

30 January 2013

Timeframe (date): 2013-01-30
Complete: Yes
3
Milestone:

22-07 3rd contribution of $220,000 (indexed to CPI)

Timeframe:

30 January 2014

Timeframe (date): 2014-01-30
Complete: Yes
4
Milestone:

22-07 4th contribution of $220,000 (indexed to CPI)

Timeframe:

30 January 2015

Timeframe (date): 2015-01-30
Complete: Yes
5
Milestone:

22-07 5th contribution of $220,000 (indexed to CPI)

Timeframe:

30 January 2016

Timeframe (date): 2016-01-25
Complete: Yes
OFFSET 6 Offset funds, Onground management None Complete
1
Milestone:

22-08 Contribution of $300,000

Timeframe:

30 January 2012

Timeframe (date): 2012-01-30
Complete: Yes
OFFSET 7 Other None Current
1
Milestone:

22-09 Provision of $250,000 contingency fund

Timeframe:

Maintained by the Proponent until one year after the date of first shipment of product from the LNG plant.

Complete: Yes