Project number 3491/2
Project name

Mandurah Lateral Gas Pipeline Project

Project status Complete
Proponent(s) WA Gas Networks Pty Ltd
Project location

ROAD RESERVE STAKE HILL 6181
LOT 9037 ON PLAN 64471 MEADOW SPRINGS 6210
LOT 803 ON PLAN 31127 PARKLANDS 6180
LOT 2667 ON PLAN 64444 PARKLANDS 6180
LOT 97 ON PLAN 14984 PARKLANDS 6180
LOT 73 ON PLAN 16751 STAKE HILL 6181
LOT 74 ON PLAN 16751 STAKE HILL 6181
LOT 68 ON PLAN 16752 STAKE HILL 6181
ROAD RESERVE STAKE HILL 6181
ROAD RESERVE STAKE HILL 6181
LOT 3043 ON PLAN 16751 STAKE HILL 6181
LOT 82 ON PLAN 38270 STAKE HILL 6181
LOT 83 ON PLAN 38270 STAKE HILL 6181
ROAD RESERVE STAKE HILL 6181
LOT 604 ON PLAN 59103 STAKE HILL 6181
LOT 91 ON PLAN 741 STAKE HILL 6181
ROAD RESERVE STAKE HILL 6181
ROAD RESERVE NAMBEELUP 6207
ROAD RESERVE NAMBEELUP 6207
LOT 12 ON DIAGRAM 60239 NAMBEELUP 6207
ROAD RESERVE NAMBEELUP 6207
ROAD RESERVE NAMBEELUP 6207
LOT 88 ON PLAN 741 NAMBEELUP 6207
LOT 27 ON PLAN 24067 NAMBEELUP 6207
LOT 4638 ON PLAN 28052 NAMBEELUP 6207
LOT 208 ON PLAN 52793 NAMBEELUP 6207
LOT 209 ON PLAN 52793 NAMBEELUP 6207
ROAD RESERVE NAMBEELUP 6207
ROAD RESERVE NAMBEELUP 6207
ROAD RESERVE NAMBEELUP 6207
LOT 73 ON PLAN 739 NAMBEELUP 6207
LOT 3 ON DIAGRAM 42627 NAMBEELUP 6207
ROAD RESERVE NAMBEELUP 6207
LOT 11 ON PLAN 14393 NORTH DANDALUP 6207
LOT 4696 ON PLAN 27217 NORTH DANDALUP 6207

Approved project area (ha) 7.93

Decision(s):

DECISION 1 Date of decision: 10 May 2010
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Land acquisition 13.85 Complete
1
Milestone:

Condition Milestone 1 - relates to permit conditions 11(a)(ii) & 11(a)(iii)

Once the Permit Holder has developed an offset proposal, the Permit Holder must provide that offset proposal to the CEO for the CEO's approval.

Timeframe:

Prior to undertaking any clearing to which the offset relates, and prior to implementing the offset. Clearing shall not commence until and unless the CEO has approved the offset proposal to which the clearing relates.

Complete: Yes
2
Milestone:

Condition Milestone 2 - relates to permit condition 11(a)(iv)

The Permit Holder shall implement the offset proposal approved under condition 11(a)(iii).

Timeframe:

Prior to the permit expiry date.

Timeframe (date): 2015-02-21
Complete: Yes