Project number 818/5
Project name

State-wide Purpose Permit Activities

Project status Current
Proponent(s) Commissioner of Main Roads Western Australia
Project location

Refer to residual impact field for a list of projects and their location details

Approved project area (ha) 0.87

Decision(s):

DECISION 1 Date of decision: 07 Oct 2010
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Rehabilitation 2.0 Current
1
Milestone:

Condition Milestone 1 - relates to CPS 818/5 permit conditions 5(a)(ii) & 15(b)
 
Once the permit holder has developed an offset proposal, the permit holder must provide that offset proposal to the CEO for the CEO's approval.

Timeframe:

Prior to clearing and prior to implementing the offset.

Complete: Yes
2
Milestone:

Condition Milestone 2 - relates to CPS 818/12 permit condition 13(e)
 
If it is necessary to modify the offset proposal approved by the CEO, then the permit holder must provide that modified offset proposal to the CEO for the CEO's approval.

Timeframe:

Prior to implementing the modified offset.

Complete: Yes
3
Milestone:

Condition Milestone 3 - relates to CPS 818/12 permit condition 13(f)
 
The permit holder must implement the latest version of the offset proposal approved by the CEO.

Timeframe:

For the term of the permit.

Complete: No
OFFSET 2 Land acquisition 0.8 Complete
1
Milestone:

Condition Milestone 1 - relates to CPS 818/5 permit conditions 5(a)(ii) & 15(b)
 
Once the permit holder has developed an offset proposal, the permit holder must provide that offset proposal to the CEO for the CEO's approval.

Timeframe:

Prior to clearing and prior to implementing the offset.

Complete: Yes
2
Milestone:

Condition Milestone 2 - relates to CPS 818/12 permit condition 13(e)
 
If it is necessary to modify the offset proposal approved by the CEO, then the permit holder must provide that modified offset proposal to the CEO for the CEO's approval.

Timeframe:

Prior to implementing the modified offset.

Complete: Yes
3
Milestone:

Condition Milestone 3 - relates to CPS 818/12 permit condition 13(f)
 
The permit holder must implement the latest version of the offset proposal approved by the CEO.

Timeframe:

For the term of the permit.

Complete: Yes