Project number OEPA:6
Project name

Anketell Point Port Development

Project status Current
Proponent(s) API Management Pty Limited (Australian Company Number 112 677 595)
Project location

Anketell Point

Approved project area (ha) 3995.0

Decision(s):

DECISION 1 Date of decision: 30 Jan 2013
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Offset funds, Research None Current
1
Milestone:

20-2 1st payment of $750,000.

Timeframe:

At least 18 months prior to infrastructure construction commencing

Complete: No
OFFSET 2 Offset funds, Research None Current
1
Milestone:

20-3 1st payment of $150,000

Timeframe:

At least six months prior to port marine infrastructure construction commencing.

Complete: No
OFFSET 3 Offset funds, Research None Current
1
Milestone:

20-4 1st payment of $625,000

Timeframe:

At least six months prior to port marine infrastructure construction commencing

Complete: No
OFFSET 4 Offset funds, Onground management, Research None Current
1
Milestone:

22-05 1st payment of $200,000

Timeframe:

At least six months prior to port marine infrastructure construction commencing

Complete: No
OFFSET 5 Offset funds, Onground management None Current
1
Milestone:

20-6 1st payment of $200,000

Timeframe:

At least six months prior to port marine infrastructure construction commencing

Complete: No