Project number OEPA:25
Project name

Rockingham Industrial Zone (Strategic Environmental Assessment)

Project status Current
Proponent(s) LandCorp
Project location

Rockingham

Project bioregion(s) Swan Coastal Plain
Assessment criteria Flora and Vegetation, Inland Waters Environmental Quality
Residual impact

Following the implementation of all mitigation measures, the proposal would have significant residual impacts:
- Clearing of up to 14 hectares of a Threatened Ecological Community (Woodlands over Sedgelands in Holocene Dune Swales) and groundwater dependent wetlands.
- Loss of up to 17 conservation category wetlands (damplands and sumplands), mostly less than 1 hectare in size.

Offset conditions

Conservation Area

5-1 Within 6 months of the date of this statement the proponent shall fence the Conservation Area, as delineated by Figure 1 and Table 2, to assist in preventing unauthorised access, and shall maintain the fencing until such time as the land is ceded to the Conservation Commission of Western Australia.

5-2 Within 6 months of the date of this statement the proponent shall remove all dumped rubbish from the Conservation Area and thereafter the proponent shall maintain the Conservation Area free of rubbish until such time as the land is ceded to the Conservation Commission of Western Australia.

5-3 Within two years of the date of this statement the proponent shall prepare an Initial Conservation Area Management Plan for the Conservation Area to the satisfaction of the Chief Executive Officer of the Office of the Environmental Protection Authority on advice from the Department of Environment and Conservation. The objective of this Initial Conservation Area Management Plan is to improve the condition of the Conservation Area to a level suitable for incorporation into the Conservation Estate. The Initial Conservation Area Management Plan will address:
1. Protecting and rehabilitating the threatened ecological community Sedgelands in Holocene dune swales of the Southern Swan Coastal Plain]
2. Maintenance of fencing of the area to control access to designated areas within the Conservation Area;
3. Design and implementation of appropriate monitoring of the vegetation within the Conservation Area, including the threatened ecological community Sedgelands in Holocene dune swales of the Southern Swan Coastal Plain;
4. Design and implementation of appropriate monitoring of hydrology including groundwater levels and quality and contingencies in the event of unacceptable hydrological impacts;
5. Maintaining the Conservation Area free of dumped rubbish;
6. Rehabilitation of degraded areas within the Conservation Area including tracks not required for strategic access;
7. The control of feral animal populations in the Conservation Area;
8. Weed control in the Conservation Area;
9. Fire prevention and response;
10.Enhancement of the fauna habitat in the area by providing harvested and artificial breeding infrastructure for significant fauna;
11. Using artificial polishing drainage basins outside of the Conservation Area, for the re-infiltration of stormwater into the Conservation Area; and
12.Completion criteria for handover to another management authority.

5-4 The proponent shall implement the Initial Conservation Area Management Plan required by Condition 5-3 until the Conservation Area is ceded to the Conservation Commission of Western Australia

5-5 When the completion criteria of Condition 5-3-12 are met, or within two years of a written request from the Department of Environment and Conservation, the proponent will arrange to cede the Conservation Area to the Conservation Commission of Western Australia.

5-6 Within one year of ceding land (pursuant to Condition 5-5) the proponent shall prepare a Conservation Area Management Plan to the satisfaction of the Chief Executive Officer of the Office of the Environmental Protection Authority on advice from the Department of Environment and Conservation. The objective of this Conservation Area Management Plan is to guide continued management of the conservation values of the area. The Conservation Area Management Plan will address:

1. Protecting and rehabilitating the threatened ecological community Sedgelands in Holocene dune swales of the Southern Swan Coastal Plain]
2. Maintenance of fencing of the area to control access to designated areas within the Conservation Area;
3. Ongoing vegetation monitoring of the threatened ecological community Sedgelands in Holocene dune swales of the Southern Swan Coastal Plain;
4. Ongoing monitoring of hydrology including groundwater levels and quality and implementation of contingencies in the event of unacceptable hydrological impacts;
5. Management of rehabilitated areas within the Conservation Area
6. The control of feral animal populations in the Conservation Area;
7. Weed control in the Conservation Area;
8. Fire prevention and response;
9. Enhancement of the fauna habitat in the area by providing harvested and artificial breeding infrastructure for Carnaby's Cockatoos; and
10.Using artificial polishing drainage basins outside of the Conservation Area for the re-infiltration of stormwater into the Conservation Area.

Offset
7-1 Within two years of the date of this statement the proponent shall prepare an Offsets Package to the requirements of the Chief Executive Officer of the Office of the Environmental Protection Authority on advice from the Department of Environment and Conservation that will ensure the rehabilitation of at least 9 hectares of threatened ecological community Sedgelands in Holocene dune swales of the Southern Swan Coastal Plain, outside of the Strategic Environmental Assessment boundary, that requires active management in land managed by the Department of Environment and Conservation and at other high priority sites in the Rockingham region.

7-2 The proponent shall implement the Offsets Package required by Condition 7-1 within three years of the date of this statement.

Statutory process EP Act Environmental Impact Assessment (Part IV)
Approved project area (ha) 540.9

Decision(s):

DECISION 1
Date: 2011-05-26 Ministerial statement: 863
OFFSET 1
Condition status: Current
Type(s): Onground management, Rehabilitation
Rationale:

The proponent will implement a 90.5 hectare Conservation Area within the proposal area that contains:
- 12 conservation category wetlands;
- 19 hectares of Threatened Ecological Community (TEC) (Woodlands over Sedgelands in Holocene Dune Swales); and
- important environmental values including very good condition vegetation, significant fauna habitat and unique landforms.

This offset avoids impacts on the development site and protects and improves these environmental values. The offset is like-for-like and local and will provide a long lasting benefit.

A minimum of 2:1 ratio was considered appropriate for the TEC; this gives a requirement of 28ha. The Conservation Area contributes approximately 19 hectares. Offset 2 will result in the need for a further 9 hectares offsite.

Security arrangements:

The offset will be ceded to the Crown for conservation to be vested to the Conservation Commission.

Governance arrangements:

A Conservation Area Management Plan will outline how the Conservation Area will be managed to ensure the protection of its environmental features.

Offset location:

Rockingham.

Approved offset area (ha): 90.5
Bioregion(s): Swan Coastal Plain
Delivery agent:

The proponent.

CONDITION MILESTONE 1
Milestone:

5-1 Fence the Conservation Area

Timeframe:

Within 6 months of the date of this statement.

Timeframe (date): 2011-11-26
Complete: Yes
CONDITION MILESTONE 2
Milestone:

5-2 Maintain the Conservation Area free of rubbish until the area is ceded to the Crown.

Timeframe:

Ongoing.

Complete: No
CONDITION MILESTONE 3
Milestone:

5-2 Remove all rubbish from the Conservation Area

Timeframe:

Within 6 months of the date of this Statement.

Timeframe (date): 2011-11-26
Complete: Yes
CONDITION MILESTONE 4
Milestone:

5-3 Prepare an Initial Conservation Area Management Plan

Timeframe:

Within two years of this Statement

Timeframe (date): 2013-05-26
Complete: Yes
CONDITION MILESTONE 5
Milestone:

5-4 Implement the Initial Conservation Area Management Plan, once approved, until the Conservation Area is ceded to the Conservation Commission of Western Australia

Timeframe:

Ongoing

Complete: No
CONDITION MILESTONE 6
Milestone:

5-5 The proponent will arrange to cede the Conservation Area to the Conservation Commission of Western Australia.

Timeframe:

Once the completion criteria are met, or within two years of a request of the Department of Parks and Wildlife.

Complete: No
CONDITION MILESTONE 7
Milestone:

5-6 Prepare an updated Conservation Area Management Plan

Timeframe:

Within one year of ceding land in condition 5-5.

Complete: No
  • No implementation milestones defined.
OFFSET 2
Condition status: Current
Type(s): Offset funds, Onground management
Rationale:

This offset proposes the acquisition and management of a further 9 hectares of threatened ecological community (Woodlands over Sedgelands in Holocene Dune Swales). A 2:1 offset ratio was considered appropriate; this gives a requirement to protect 28 hectares. Offset 1 protects approximately 19 hectares within the Conservation Area.

This offset is like-for-like and local and will provide a long lasting benefit.

~~~

The approved offset package involves the protection and enhancement of 10 hectares of the threatened ecological community (Woodlands over Sedgelands in Holocene Dune Swales) plus 22 hectares of buffer area within Port Kennedy Scientific Park. The offset will focus on preventing unauthorised vehicle access and weed control.

Security arrangements:

Within State Conservation tenure.

Governance arrangements:

Offset location:

Rockingham

Approved offset area (ha): 9.0
Bioregion(s): Swan Coastal Plain
Delivery agent:

Department of Parks and Wildlife

CONDITION MILESTONE 1
Milestone:

7-1 Prepare an Offsets Package for the approval of the CEO

Timeframe:

Within two years of the date of this statement.

Timeframe (date): 2013-05-26
Complete: Yes
CONDITION MILESTONE 2
Milestone:

7-2 Implement the Offsets Package

Timeframe:

Within three years of the date of this statement.

Timeframe (date): 2014-05-26
Complete: Yes
  • No implementation milestones defined.
DECISION 2
Date: 2014-06-18 Ministerial statement: 973
OFFSET 1
Condition status: Current
Type(s): Onground management
Rationale:

This is a derived proposal for the Rockingham Industrial Zone Strategic Environmental Assessment. Offset 1 under Decision 1 is relevant for this proposal, with the following offset conditions applied for this proposal:

5-1 The proponent shall maintain the fence that it established around the Conservation Area, until such time as the Conservation Area is ceded to the Conservation Commission of Western Australia.

5-2 The proponent shall maintain the Conservation Area free of rubbish until such time as the land is ceded to the Conservation Commission of Western Australia.

5-4 The proponent shall implement the Initial Conservation Area Management Plan that was approved by the CEO on 23 December 2013, or subsequent revisions as approved by the CEO, until the Conservation Area is ceded to the Conservation Commission of Western Australia.

5-5 When the completion criteria detailed in the Initial Conservation Area Management Plan referred to in condition 5-4 are met, or within two years of a written request from the Department of Parks and Wildlife, the proponent will arrange to cede the Conservation Area to the Conservation Commission of Western Australia.

Security arrangements:

Governance arrangements:

Offset location:

Approved offset area (ha): None
Bioregion(s):
Delivery agent:

  • No condition milestones defined.
  • No implementation milestones defined.
OFFSET 2
Condition status: Current
Type(s): Rehabilitation
Rationale:

This is a derived proposal for the Rockingham Industrial Zone Strategic Environmental Assessment. Offset 2 under Decision 1 is relevant for this proposal, with the following offset condition applied for this proposal:

7-2 The proponent shall implement the Offsets Package that was approved by the CEO on 10 October 2013 within six months of the date of this statement, or by a later date agreed by the CEO.

Security arrangements:

Governance arrangements:

Offset location:

Approved offset area (ha): None
Bioregion(s):
Delivery agent:

  • No condition milestones defined.
  • No implementation milestones defined.
DECISION 3
Date: 2015-02-18 Ministerial statement: 995
OFFSET 1
Condition status: Current
Type(s): Onground management
Rationale:

This is a derived proposal for the Rockingham Industrial Zone Strategic Environmental Assessment. Offset 1 under Decision 1 is relevant for this proposal, with the following offset conditions applied for this proposal:

5-1 The proponent shall maintain the fence that it established around the Conservation Area until such time as the Conservation Area is ceded to the Conservation Commission of Western Australia.

5-2 The proponent shall maintain the Conservation Area free of rubbish until such time as the land is ceded to the Conservation Commission of Western Australia.

5-4 The proponent shall implement the Initial Conservation Area Management Plan that was approved by the CEO on 23 December 2013, or subsequent revisions as approved by the CEO, until the Conservation Area is ceded to the Conservation Commission of Western Australia.

5-5 When the completion criteria detailed in the Initial Conservation Area Management Plan referred to in condition 5-4 are met, or within two years of a written request from the Department of Parks and Wildlife, the proponent will arrange to cede the Conservation Area to the Conservation Commission of Western Australia.

Security arrangements:

Governance arrangements:

Offset location:

Approved offset area (ha): None
Bioregion(s):
Delivery agent:

  • No condition milestones defined.
  • No implementation milestones defined.
DECISION 4
Date: 2016-12-06 Ministerial statement: 1043
OFFSET 1
Condition status: Current
Type(s): Onground management
Rationale:

This is a derived proposal for the Rockingham Industrial Zone Strategic Environmental Assessment. Offset 1 under Decision 1 is relevant for this proposal, with the following offset conditions applied for this proposal:

5-1 The proponent shall maintain the fence that it established around the Conservation Area until such time as the Conservation Area is ceded to the Conservation and Parks Commission

5-2 The proponent shall maintain the Conservation Area free of rubbish until such time as the land is ceded to the Conservation and Parks Commission.

5-4 The proponent shall implement the Initial Conservation Area Management Plan that was approved by the CEO on 23 December 2013, or subsequent revisions as approved by the CEO, until the Conservation Area is ceded to the Conservation and Parks Commission.

5-5 When the completion criteria in Section 5.3 of the Initial Conservation Area Management Plan referred to in condition 5-4 are met, or within two years of a written request from the Department of Parks and Wildlife, the proponent will arrange to cede the Conservation Area to the Conservation and Parks Commission.

Security arrangements:

Governance arrangements:

Offset location:

Approved offset area (ha): None
Bioregion(s):
Delivery agent:

  • No condition milestones defined.
  • No implementation milestones defined.