Project number 5375/1
Project name

Clearing of 0.3 hectares of native vegetation for the purpose of road realignment in the Shire of Chapman Valley.

Project status Current
Proponent(s) Shire of Chapman Valley
Project location

LOT 11854 ON PLAN 189517 NANSON 6532
PART LOT 119 ON PLAN 232020 NANSON 6532
ROAD RESERVE NABAWA 6532
ROAD RESERVE NABAWA 6532

Approved project area (ha) 0.3

Decision(s):

DECISION 1 Date of decision: 17 Jan 2013
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Rehabilitation 0.9 Current
1
Milestone:

Condition Milestone 1 - relates to Permit condition 11(a)

Retain the vegetative material and topsoil removed by clearing and stockpile the vegetative material and topsoil in an area that has already been cleared.

Timeframe:

Following clearing.

Complete: No
2
Milestone:

Condition Milestone 2 - relates to Permit condition 11(b)

Revegetate and rehabilitate within the areas cross-hatched red on Plan 5375/1 by:
(i) re-shaping the surface of the land so that it is consistent with the surrounding 5 metres of uncleared land; and
(ii) ripping the ground on the contour to remove soil compaction; and
(iii) laying the vegetative material and topsoil retained under condition 11(a) on the red hatched area(s).

Timeframe:

Within 6 months following clearing.

Complete: No
3
Milestone:

Condition Milestone 3 - relates to Permit condition 11(c)

(i) engage an environmental specialist to determine the species composition, structure and density of the area revegetated and rehabilitated; and
(ii) where, in the opinion of an environmental specialist, the composition structure and density determined under condition 11(c)(i) will not result in a similar species composition, structure and density to that of pre-clearing vegetation types in that area, revegetate the area by deliberately planting and/or direct seeding native vegetation that will result in a similar species composition, structure and density of native vegetation to pre-clearing vegetation types in that area and ensuring only local provenance seeds and propagating material are used.

Timeframe:

Within 18 months of laying the vegetative material and topsoil on the cleared area in accordance with condition 11(b).

Complete: No
4
Milestone:

Condition Milestone 4 - relates to Permit condition 11(d)

Where additional planting or direct seeding of native vegetation is undertaken in accordance with condition 11(c)(ii), the Permit Holder shall repeat condition 11(c)(i) and 11(c)(ii).

Timeframe:

Within 24 months of undertaking the additional planting or direct seeding of native vegetation.

Complete: No
5
Milestone:

Condition Milestone 5 - relates to Permit condition 11(e)

Where a determination by an environmental specialist that the composition, structure and density within areas revegetated and rehabilitated will result in a similar species composition, structure and density to that of pre-clearing vegetation types in that area, as determined in condition 11(c)(i) and (ii), that determination shall be submitted for the CEO’s consideration. If the CEO does not agree with the determination made under condition 11(c)(ii), the CEO may require the Permit Holder to undertake additional planting and direct seeding in accordance with the requirements under condition 11(c)(ii).

Timeframe:

For the term of the permit.

Timeframe (date): 2023-02-08
Complete: No