Project number 3956/2
Project name

Clearing of 16.82 hectares of native vegetation for the purpose of limestone and sand extraction in the City of Mandurah.

Project status Current
Proponent(s) PMR Quarries Pty Ltd
Project location

LOT 5 ON PLAN 12441 HERRON 6211

Approved project area (ha) 16.82

Decision(s):

DECISION 1 Date of decision: 22 Dec 2011
Offset Offset Type Offset Area Offset Status Condition Milestones
OFFSET 1 Rehabilitation 8.9 Current
1
Milestone:

Condition Milestone 1 - relates to Permit condition 12(a)(i)

The Permit Holder shall revegetate and rehabilitate the area hatched red on Plan 3956/2 (portion of Lot 5 on Plan 12441) by ripping the ground on the contour to remove soil compaction.

Timeframe:

Within 12 months of commencement of clearing.

Complete: No
2
Milestone:

Condition Milestone 2 - relates to Permit condition 12(a)(ii), (iii) & (iv)

The Permit Holder shall revegetate and rehabilitate the area hatched red on Plan 3956/2 by:
- deliberately planting and/or direct seeding native vegetation to a density of 1000 trees per hectare;
- the species shall consist of Banksia species, Eucalyptus gomphocephala, Eucalyptus marginata and Corymbia calophylla; and
- ensuring only local provenance seeds and propagating material are used to revegetate and rehabilitate the area.

Timeframe:

Within 12 months of commencement of clearing.

Complete: Yes
3
Milestone:

Condition Milestone 3 - relates to Permit condition 12(b)(i)

The Permit Holder shall engage an environmental specialist to determine the density of the tree species under condition 12(a)(iii) in the area revegetated and rehabilitated.

Timeframe:

Within 24 months of undertaking revegetation and rehabilitation in accordance with condition 12(a).

Complete: No
4
Milestone:

Condition Milestone 4 - relates to Permit condition 12(b)(ii)

Where, in the opinion of an environmental specialist, the density determined under condition 12(b)(i) is less than 800 trees per hectare, the Permit Holder must undertake additional planting or direct seeding of native vegetation in accordance with the requirements of condition 12(a)(ii),(iii) and (iv).

Timeframe:

Within 24 months of undertaking revegetation and rehabilitation in accordance with condition 12(a).

Complete: No
5
Milestone:

Condition Milestone 5 - relates to Permit condition 12(c)

Where additional planting or direct seeding of native vegetation is undertaken in accordance with condition 12(b)(ii), the Permit Holder shall repeat condition 12(b)(i) and 12(b)(ii)

Timeframe:

Within 24 months of undertaking the additional planting or direct seeding of native vegetation.

Complete: No
6
Milestone:

Condition Milestone 6 - relates to Permit condition 12(d)

Where a determination by an environmental specialist that the density within areas revegetated and rehabilitated will result in a density of at least 800 trees per hectare, as determined in condition 12(b)(i) and (ii), the Permit Holder shall submit that determination for the CEO’s consideration. If the CEO does not agree with the determination made under condition 12(b)(ii), the CEO may require the Permit Holder to undertake additional planting and direct seeding in accordance with the requirements under condition 12(b)(ii).

Timeframe:

For the term of the Permit.

Timeframe (date): 2021-03-28
Complete: No